Double S Construction — Big Springs, TX
Ground conditions: Solid limestone and iron rock Project: Placing conduits for power and control cables for a wind generator farm. Bores ranged from 150-200′; installing 6-inch conduit for main electric cables to deliver the generated power & a 2-inch conduit for the control cables at a spacing of 3-feet apart. The conduits were placed by … Continued